CAG Report Reveals Increased Costs but No Additional Benefits for Kaleshwaram Project
The CAG has accused the Water Resources Department of awarding contracts for 17 works valued at Rs. 25,000 crores before the approval of the Detailed Project Report (DPR). The capital cost per acre for irrigation water through the Kaleshwaram project is reported to be Rs. 6.42 lakhs, as per the CAG's findings. The expected benefit-to-cost ratio of the project was estimated at 1:51, but it currently stands at 0.75, with a likelihood of further decrease.
Additionally, the report mentions that a comprehensive seismic study was not conducted before the construction of the Mallanna Sagar reservoir.