TG RERA cracks down on realty violations, orders refunds and delayed possession interest

TG RERA cracks down on realty violations, orders refunds and delayed possession interest

Listen to this story

Hyderabad, November 26: The Telangana Real Estate Regulatory Authority (TG RERA) imposed penalties totalling ₹2.13 crore on three real estate developers for statutory violations and ordered refunds, delayed possession interest and completion of pending infrastructure across several residential projects in a series of rulings issued on November 25.

The authority imposed the highest penalty of ₹2 crore on Aliens Developers Private Limited in connection with its Aliens Space Station Township project at Tellapur in Sangareddy district.

Acting on a complaint filed by A. Nagalakshmi and V. Nagarjun Yadav, TG RERA found that the developer had collected more than 10 per cent of the property value without executing a registered agreement for sale, violating Section 13 of the Real Estate (Regulation and Development) Act, 2016.

The authority also found that the draft agreement furnished by the developer contained provisions inconsistent with statutory requirements, including those governing compensation for delayed possession.

Aliens Developers was directed to pay the penalty within 60 days and furnish a legally compliant agreement within seven days. If the developer failed to specify a definite possession date and the purchasers opted to withdraw, it would have to refund ₹42,11,898 with interest at 10.85 per cent per annum.

In another significant ruling, TG RERA directed the initiation of suo motu proceedings against Bhuvanteza Infra Projects Private Limited and Green Metro Infratech Projects Private Limited over the sale of flats in the Tulasi Bhagyanagar project at Dundigal before obtaining requisite approvals and registration.

Four purchasers had collectively paid ₹1.36 crore, including ₹96 lakh collected from three purchasers before the requisite approvals and registration were obtained.

Holding both companies jointly and severally responsible, the authority directed them to pay delayed possession interest at 10.85 per cent per annum, complete pending amenities, obtain the occupancy certificate and hand over the flats.

TG RERA also imposed a penalty of ₹10,06,916 on Akshita Infra for misleading promotional material concerning its Akshita Heights plotted development, which advertised a gated layout despite the boundary wall not being part of the sanctioned plan.

ELV Developers was penalised ₹3,20,339 for collecting advances exceeding the statutory limit without executing a registered agreement for sale. The developer was also directed to pay interest on the amounts subsequently refunded to the purchaser.

Alekya Infra Developers was ordered to refund ₹17,42,250 with interest after a plot in its NSR County Phase II project was subsequently sold to a third party.

The authority directed Vasavi Realtors LLP to pay delayed possession interest to purchasers in the Vasavi Lake City project and ordered Bharati Builders to refund ₹9.30 lakh each in two separate complaints concerning Bharathi's Lake View Apartments at Kompally.

In five complaints concerning ELV Cosmopolis at Adibatla, TG RERA directed ELV Projects Private Limited to complete pending construction and provide essential amenities within six months, besides obtaining an occupancy certificate within three months of completing the works.

The authority also issued directions concerning electricity infrastructure, parking allotments and the formation of associations of allottees in other residential developments.